February, 2016
Hindsight | Insight | Foresight
February, 2016
This is a repeating eventFeb 11 2020
The main turret bearing on a FPSO vessel seized and subsequently failed, resulting in the vessel being unable to weathervane. Production was resumed with a revised operating regime employing tugs
The main turret bearing on a FPSO vessel seized and subsequently failed, resulting in the vessel being unable to weathervane. Production was resumed with a revised operating regime employing tugs to maintain a constant heading. Subsequently, the vessel was converted to employ a permanent spread moored configuration, fixing the heading of the vessel and installing an associated deepwater offloading buoy.
[ Property Damage $450 Million. Estimated Current Value $466 Million ]
Image credit: Tullow Oil